Join Our Email List   |   facebookFacebook   |   Mk II forumMk II Forum

2017-01-27: Project GMT Update

Quick update on the project:

  • I have completed the preliminary schedule for the remaining Key West deliveries. We will start updating the system after we contact some stragglers.
  • A new delivery of the white/gilt and black/gilt dials have arrived. We still need to do the QC.

2017-01-26 (3:24 pm) Addendum:

  • As noted in the ordering emails you are free to change your order up until your order reaches “3.0 Build in Process”. However please note that given that the supply of parts may be tight for some models and in fairness to the other customers, any order change request will be subject to the availability of parts. If the supply is tight for a particular model we may have to push any orders for customers that make changes to their orders to the back of the queue to ensure there are enough parts available. If we for any reason we can’t accommodate your order change we will deliver based on the original order. So the cut-off “date” for this policy to go into effect will be when the scheduling has been completed. We will do our best to be as accommodating as possible and will only invoke this policy as required.

2017-03-20 (Clarification): Please note that this post is meant to be read in context with the following post from 2016-09-13 where it notes:

“Scheduling: I have been waiting to make a big announcement about publishing the entire delivery schedule but based on the last few months’ of work any projections more than a few weeks into the future will not prove to be terribly accurate. The reason for this is that the dials are quite difficult to work with and this leads to a higher level of re-work than with standard painted dials. What we will do is publish dates for those customers where shipment is expected within a 2-4 week window. For everyone else we will report on the Group # that we are working at the moment and provide a rough projection as to when the next Group # will be begun. That should allow me to provide more updates without having to spend a lot of time revising specific ship dates with all of the orders.”

 

2017-12-07: Project 300 Update

  • Case parts are in the final phases of manufacturing
  • The bracelet end-link has been approved for mass production and production is currently in process
  • Best estimate right now is that we will begin QC of the case parts in Q1 of 2017. If all goes well delivery should be able to begin in the summer of 2017
  • We will be taking photos and preparing the web site for receipt of final selections and payments. We expect that we will start ordering for the Plankowners in February/March of 2017. We will follow the same process as we did with the Project GMT where we will open up ordering in batches. The expectation is that we will contact one group approximately each month.

Thank you for your support and patience.

This will likely be the last update before 2017 so we wanted to wish everyone a wonderful holiday season and all the best for 2017!

2016-12-07: Project GMT Update

  • The case parts that we need for the remainder of the Project GMT have largely been delivered. We will begin the QC of those parts after the holidays. There are a few exceptions. We are still waiting on the bezels and the bracelets. However this should not effect the timetable significantly since there is plenty to do in the mean time.
  • Parts still on order: White/gold and Black/gold dials as well as the bezel inlays. We are delaying the final ordering of the inlays because we want to get all the orders in so we can order enough parts to fill those orders. Since there is plenty of assembly to do in the mean time this strategy should not adversely effect the timetable.
  • The ordering emails for Group 9 and 10 will go out today.
  • I was fighting a cold for the first 3 weeks of November. I am back to full strength now but busier than expected due to the work that we have to make up. We are working on the scheduling right now and expect to have more done during January.
  • Progress: We are nearly done with the Plankowner and Group 1 deliveries. There is one Plankowner and one Group 1 order current remaining to be delivered. We are also working on Group 2 and 3 orders right now. My apologies, if it were not for November we would have had better news to report on this front.

Thank you for your support and patience.

This will likely be the last update before 2017 so we wanted to wish everyone a wonderful holiday season and all the best for 2017!

Heads up: Delays in replies

Just wanted to let everyone know that my ability to respond to the order status emails will be limited over the next two weeks. I have to complete the review of the Nassau/Key West mass production samples and get those parts into mass production. We want to bring the Nassau back and minimize any delays in shipments for Groups 6-10 of the Key West. Thanks in advance for your patience and understanding.

2016-09-27: Hawkinge non-date

The latest shipment of the Hawkinge non-date watches has arrived and we are currently QA’ing the delivery. We will post an update and send out an email when they will be ready for ordering.

2016-09-27: Project 300 Update

We got word earlier today that the case parts are expected to be completed in Q1 of 2017. The bracelet end-link will be ready for our review before the end of the year. As noted before we do not expect that the bracelet end-link re-design will impact the delivery timetable since we expect to be preoccupied with the QC of the case parts while the bracelets are being manufactured.

In the mean time we will be working on the following:

* Manufacturing and QC’ing the hands we will need for this project

* Reviewing the dial samples and getting the dials into mass production